Planned does not mean ready
A work order can be planned without the labour, materials, access, permits or operating conditions required to execute it.
10 August 2026
A job can have a scope, duration and scheduled date and still not be ready to start.
Maintenance systems often treat planning status as if it were a single property of the work order. Operational readiness is more demanding.
Readiness is a relationship between constraints
A job may depend on:
- the correct people and competencies;
- parts and repairables;
- tools or lifting equipment;
- site access;
- isolations and permits;
- contractor mobilisation;
- prerequisite work;
- production release of the asset.
Until those conditions are satisfied, the planned date is only an intention.
scope
+ labour
+ materials
+ access
+ controls
+ dependencies
= executable work
Representing readiness explicitly makes weekly schedules and shutdown plans more useful because the system can distinguish work that is merely listed from work that has a reasonable chance of being executed.